Based on Nakano City, JR East and Tokyo Metro announcements and city documents, including Nakano City’s station-area Q&A (updated July 17, 2026); checked October 24, 2026. Dates in the future are plans and may change. The photos on this page were taken in July 2023 and February 2025, before the new west gate opened.
Nakano is one stop west of Shinjuku on the JR Chūō Line rapid service, and the Tokyo Metro Tōzai Line starts here. For fifty years its landmark was Nakano Sunplaza, the white, wedge-shaped tower with a concert hall beside the north exit. In 2026 the station area is changing on two clocks: a new west side of the station is due to open in December, while the Sunplaza site, after its first redevelopment plan collapsed, is being planned again with a completion target in the mid-2030s.
Already there: the north exit, Sun Mall and Nakano Broadway
From the north exit, the covered shopping street Nakano Sun Mall runs north; walk straight through it and you reach Nakano Broadway. Nakano City’s official tourism site describes Broadway as a shopping complex opened in 1966, with shops on the basement to fourth floors and homes on the floors above, and more than 241 shops of many kinds (as of 2022). Since the 1980s, the city says, it has been known as a centre of otaku culture and as a place for watches, drawing visitors from Japan and abroad. The same site lists shops for trading cards, model railways, model cars and capsule toys inside the building.
To the west of the north exit stands Nakano Sunplaza. It opened in 1973 as a national youth workers’ centre and closed on July 2, 2023, after fifty years, ahead of the planned redevelopment (Nakano City public-relations bulletin, July 5, 2023). The building is still standing. Nakano City took over its land and buildings as a donation on September 5, 2025, and since October 31, 2025 has opened the plaza on its south side as the “Nakano Sunplaza Performance Field”: musicians, dancers and street performers who register with the city can use it free of charge, from 9:00 to 21:00 every day. On November 7–8, 2026, the area’s autumn street festival, Nakano Nigiwai Festa, uses the Sunplaza south plaza together with Nakano Sun Mall, Nakano Broadway and other shopping streets.

December 6, 2026: a new west gate
On July 7, 2026, Nakano City, JR East, Tokyo Metro and UR (the Urban Renaissance Agency) jointly announced that a new west north–south passage and a bridge station building will open on Sunday, December 6, 2026, at noon (planned). Nakano City’s announcement gives these figures:
| Item | Plan (Nakano City, July 7, 2026) |
|---|---|
| West north–south passage | About 80 m long and 19 m wide, connecting a new north exit (新北口) and a new south exit (Momozono exit, 新南口・桃園口), with the West Gate on its second floor |
| West Gate | 7 ticket machines and 8 ticket gates |
| Lifts and escalators | 4 lifts (15 people each) and 8 escalators, plus lifts and escalators on each platform |
| Other facilities | Toilets (including an accessible toilet) and a baby room in the concourse |
| Shops | 6 station shops (ekinaka) open on December 6; the station building Atre Nakano, with about 70 shops on about 7,300 m², opens on December 9 |
| Safety | The passage becomes a third main evacuation route across the tracks, in addition to Nakano-dōri and Momijiyama-dōri |
What will be finished, and what will not

| Status | |
|---|---|
| Already there | North exit, Nakano Sun Mall, Nakano Broadway; the closed Sunplaza building, with its south plaza open for performances and events |
| Planned for December 6, 2026 | West passage, West Gate and station shops; the new south exit (Momozono exit, 新南口・桃園口) and Nakano Station Momozono Plaza (中野駅桃園広場) in front of it; parts of two pedestrian decks on the north side. Atre Nakano follows on December 9 |
| Later | South exit station plaza (南口駅前広場), being enlarged together with the Nakano 2-chome redevelopment, a separate project from the new Momozono exit: planned for October 2028, and still under construction when the west gate opens. New north exit plaza (新北口駅前広場): completion in fiscal 2029 (by March 2030), with bus stops, a taxi pool and decks of about 175 m and 170 m. Sunplaza site: see below |
The Sunplaza site: a plan that stopped and restarted
Nakano City’s page on the north exit area lists the steps of the original plan: a redevelopment business plan adopted in January 2020, a planned developer chosen in May 2021, and city planning decisions in November 2023. In July 2023, the city’s bulletin described the provisional “NAKANO Sunplaza City”, with a hall for up to 7,000 people.
That plan did not go ahead. According to a ward assembly committee paper of October 10, 2025, construction cost estimates rose sharply; the planned developer withdrew its application for approval in October 2024, and the basic agreement between the developer and the landowners was ended at the end of June 2025. The city then began revising the plan. Its documents show how the project has been rethought:
| Original plan (2020–2023) | Direction in 2026 (city documents) | |
|---|---|---|
| Hall | A hall for up to 7,000 people at the core | A hall mainly for popular music concerts, tiered seating, 3,000 seats as the base case, with 2,500–5,000 considered |
| Development method | Urban redevelopment project led by a private developer | Urban redevelopment compared with options using fixed-term land leases on city-owned land, so the land stays with the city |
| Other uses | — | Homes, offices (for the anime and content companies in Nakano), shops for families and concert-goers, and a green public square |
| Completion target | Fiscal 2028 (city bulletin, July 2023) | End of fiscal 2034 |
| Basic concept | A cultural landmark at the station | Kept: the city says the basic concept is, in principle, not being reviewed |
The new timeline
| When | What (city documents) | Status on October 24, 2026 |
|---|---|---|
| March 2026 | Direction of the revision published | Done |
| August 2026 | Outline (骨子) of the revised plan reported to the ward assembly | Done |
| Around February 2027 | Revised redevelopment business plan adopted | Planned |
| Fiscal 2027 | Public call for a private developer | Planned |
| End of fiscal 2029 (by March 2030) | Target for city planning decision | Planned |
| Fiscal 2030 | Start of construction | Planned |
| End of fiscal 2034 (by March 2035) | Target for completion | Planned |
Until then, the city plans temporary uses of the site. Its documents describe parking and a loading area on the north side of the Sunplaza land, and, as a trial from fiscal 2026, advertising by anime companies based in Nakano on the building’s walls, with fiscal 2029 set as the end of the advertising period because of the target date for demolition work. We have not confirmed whether these had started by October 2026.
Our reading: if the targets hold, the station’s west side, with the new Momozono exit, opens in December 2026; the plaza at the south exit is finished in October 2028 and the new north exit plaza in fiscal 2029. The Sunplaza tower, meanwhile, stays closed until demolition, and the new hall is a mid-2030s project. A visitor in 2027 will see a new station entrance and a new station building next to a fifty-year-old tower waiting for its replacement.
What this means if you visit
- From December 6, 2026 (planned), there will be a second way into Nakano Station on its west side, with lifts to the platforms and a new south exit, the Momozono exit. Atre Nakano is due to open on December 9.
- The route to Nakano Broadway is unchanged: north exit, then straight through Nakano Sun Mall.
- Around the north and south exits, expect construction for the plazas until about 2028–2029.
- Nakano Sunplaza is closed, but its south plaza is used for street performances and events such as the Nigiwai Festa on November 7–8, 2026.
Not surveyed on site: we have not visited the station or the construction areas for this article. Everything here comes from official announcements and city documents. We will update this page after the West Gate opens.
Sources
- Nakano City — “A new entrance on the west side of Nakano Station” (joint announcement with JR East, Tokyo Metro and UR, July 7, 2026, Japanese) (checked 2026-10-23)
- Tokyo Metro — the same joint announcement (July 7, 2026, Japanese) (checked 2026-10-23)
- Nakano City — Q&A on the Nakano Station area (updated July 17, 2026, Japanese) (checked 2026-10-24)
- Nakano City — Nakano Station new north exit area (ward office and Sunplaza district) redevelopment
- Nakano City public-relations bulletin, July 5, 2023 (PDF, Japanese): Sunplaza’s closure on July 2, 2023
- Nakano ward assembly — Construction Committee paper, October 10, 2025 (PDF): background to the plan revision
- Nakano City — Mayor’s press briefing, October 23, 2025 (PDF): temporary use of the Sunplaza plaza and land
- Nakano City — Mayor’s press briefing, March 26, 2026 (PDF): direction of the plan revision
- Nakano ward assembly — Committee paper, April 23, 2026 (PDF): advertising on the Sunplaza building
- Nakano ward assembly — Committee paper, August 28, 2026: outline of the revised redevelopment plan (PDF)
- Nakano City — Nakano Nigiwai Festa 2026 Autumn (updated October 20, 2026)
- Nakano City official tourism site “Marutto Nakano” — Nakano Broadway (PDF of the March 2022 page)